Looking forward to your E4
What you should check before delivery
Are all installation requirements met?
To make sure that there are no nasty surprises on installation day.
Is everything ready for delivery?
So that your machine arrives at your premises undamaged.
Are you equipped for all work?
To get started right away, you should have all the tools and any extra equipment Physical component which must be obtained separately and which adds new functionality to your machine. there.
Installation requirements
Choosing the installation site
The installation site must meet the following criteria:
- Firm and even surface, must be able to carry the weight of the machine.
- Alternating current source.
- An operational Residual Current Device / Ground Fault Circuit Interrupter on the electric circuit of the machine.
- Machine requires an external air extraction system.
- Access to the internet and local computer network via cable.
Length of the supplied power cord: 1.8 m (6 ft)
Length of the provided Ethernet network cable: 2 m
-
To avoid job interruptions, install an uninterruptible power supply (UPS), type online / VFI (IEC 62040-3, Class 1) if there are regular power failures or frequent mains voltage fluctuations.
-
You will need the help of your IT specialist to integrate the machine into the network. A direct connection between machine and the CAM computer The computer that is connected to your machine and which runs DentalCAM and DentalCNC. is also possible.
The technical data contains further requirements for the installation site.
This is an excerpt. The complete technical data can be found here.
Dimensions (W/D/H)
|
Unit |
Value |
Value |
Value |
---|---|---|---|---|
Footprint (approx.) |
mm in |
260 x 260 10.2 x 10.2 |
372 x 258 14.7 x 10.2 |
337 x 324 13.3 x 12.8 |
Housing fully closed (approx.) |
mm in |
360 x 370 x 490 14.2 x 14.6 x 19.3 |
455 x 550 x 630 18 x 21.7 x 24.8 |
364 x 460 x 473 14.3 x 18.1 x 18.6 |
Minimum required space for operation (approx.) |
mm in |
560 x 620 x 530 15 x 25 x 21 |
800 x 800 x 750 31.5 x 31.5 x 29.6 |
710 x 785 x 473 28.0 x 30.9 x 18.6 |
Base system
|
Unit |
Value |
Value |
Value |
---|---|---|---|---|
Weight (approx.) |
kg lbs |
29 64 |
91 201 |
52 115 |
Axes – Rotational axis A |
|
4 +190° to -10° |
5 360° / ±35° |
4 +190° to -10° |
Overvoltage category (IEC 60664-1) |
|
II |
II |
II |
External air extraction system
|
Unit |
Value |
Value |
---|---|---|---|
Minimum extraction capacity |
l/min cfm |
2,500 (at 220 hPa) 88.3 (at 3.2 psi) |
2,500 (at 220 hPa) 88.3 (at 3.2 psi) |
Suction unit |
|
Designed for the commercial use in the dental sector Equipped with a filter of the filter class M |
Designed for the commercial use in the dental sector Equipped with a filter of the filter class M |
Ambient conditions
|
Unit |
Value |
Value |
Value |
---|---|---|---|---|
Relative humidity |
|
80 %, non-condensing |
80 %, non-condensing |
80 %, non-condensing |
Ambient temperature for storage/transport |
°C °F |
‑20 – 60 -4 – 140 |
‑20 – 60 -4 – 140 |
‑20 – 60 -4 – 140 |
Ambient temperature for operation |
°C °F |
10 – 35 50 – 95 |
10 – 50 – |
10 – 35 50 – 95 |
Location type |
|
Indoor |
Indoor |
Indoor |
Maximum height above mean sea level |
m ft |
2000 6561 |
2000 6561 |
2000 6561 |
Ambient air (IEC 60664-1) |
|
Dust free, pollution degree 2 |
Dust free, pollution degree 2 |
Dust free, pollution degree 2 |
Electromagnetic radiation (IEC 61326-1) |
|
Residential, business and commercial areas |
Residential, business and commercial areas |
Residential, business and commercial areas |
Electromagnetic interference (IEC 61326-1) |
|
Industrial environment |
Industrial environment |
Industrial environment |
Sound emission
Operating condition |
Unit |
Value |
Value |
Value |
---|---|---|---|---|
Machining |
dB(A) |
74.55 |
71 dB(A) |
(Undefined variable: GLB_ProductDataN4plus.SoundPowerLevel) |
All other operating conditions |
dB(A) |
<70 |
<70 dB(A) |
<70 dB(A) |
Measuring conditions |
Value |
ValueN4+ |
Value |
---|---|---|---|
Machined material |
Composite (VITA CAD temp block) |
MEDENTIKA® PreFace® abutment, titanium, 11.5 mm |
CoCr |
Condition of the tools |
worn |
new |
new |
Measured value |
Sound pressure level (distance: 1 m) |
Sound power level |
Sound pressure level (distance: 1 m) |
Measurement according to |
ISO 3746, accuracy grade 3 |
ISO 3746, accuracy grade 3 |
ISO 3746, accuracy grade 3 |
Connections
|
Unit |
Value |
Value |
Value |
---|---|---|---|---|
Power connector (and maximum power consumption in watts) |
V AC Hz W |
100 – 240 50/60 500 Glass fuse T6,3A L250V |
100 – 240 50/60 640 Glass fuseT6,3A L250V |
100 – 240 50/60 640 Glass fuse T6,3A L250V |
Network connection – Speed |
|
RJ-45 10BASE/100BASE-TX/1000BASE-T (Auto-sensing) |
RJ-45 10BASE/100BASE-TX/1000BASE-T (Auto-sensing) |
RJ-45 10BASE/100BASE-TX/1000BASE-T (Auto-sensing) |
USB port |
|
2 x 2.0 A 1 x 2.0B |
2.0 A |
– |
DentalCAM
System requirements:
- CPU:
Single machine control: 64-bit Intel Core i CPU of the 10th generation with 4 cores and hyperthreading (e.g., Intel Core i5-10500)
Alternative: 64-bit AMD Ryzen CPU with at least 4 cores (e.g., AMD Ryzen 5 3600)
Multi-machine control: 64-bit Intel Core i CPU of the 10th generation 6 cores and hyperthreading (e.g., Intel Core i7-10700)
Alternative: 64-bit AMD Ryzen CPU with at least 6 cores and 12 threads (e.g., AMD Ryzen 5 3600)
- Operating system: 64-bit version of Windows® 10, 11
- Storage device: SSD with 512 GiB
- Random access memory:
Single machine control: 8 GiB
Multi-machine control: 16 GiB
-
Display resolution: 1920 x 1080 (Full HD)
-
A permanent Internet connection during installation and use
You can find the full installation instructions here.
Transport and unloading
-
Make sure that the installation site is easily accessible.
-
Observe the transport instructions: Transportation and storage
-
Follow the unpacking instructions: Unpacking and positioning
Tools and extra equipment
The following additional resources must be available at the installation site on the day of delivery:
-
Milling / grinding tools
Tool starter set (optional)
-
Dry machining tank for dry machining (optional)
What's next?